Russian cos must launch 3.94 GW of green power 2019–2024 - News Archive - PRIME Business News Agency - All News Politics Economy Business Wire Financial Wire Oil Gas Chemical Industry Power Industry Metals Mining Pulp Paper Agro Commodities Transport Automobile Construction Real Estate Telecommunications Engineering Hi-Tech Consumer Goods Retail Calendar Our Features Interviews Opinions Press Releases

Russian cos must launch 3.94 GW of green power 2019–2024

MOSCOW, Jul 23 (PRIME) -- Russian energy producers must launch 3.94 gigawatts (GW) of green energy from 2019 through 2024 under a state renewable energy program, according to the documents seen by PRIME on Tuesday.

The support will ensure return on investment in 15 years and a basic yield of 12% annually adjusted to the rate of OFZ state bonds.

Power producers must launch 819.8 megawatts (MW) of green power in 2019, 786 MW in 2020, 687.5 MW in 2021, 697.5 MW in 2022, 648.2 in 2023 and 297.1 MW in 2024.

End

23.07.2019 19:44